OMERS and Blackstone's TDI Team Up to Bid on Toronto's $1.5-Billion Underwater Power Line

The pension plan and the Blackstone-owned transmission developer will compete to build the Toronto Third Line, a planned 900-megawatt cable under Lake Ontario from Clarington to the Port Lands, alongside rival bidders Fortis and National Grid Ventures.

By Journal Staff ·
The white reactor buildings and domed vacuum building of the Darlington Nuclear Generating Station on the Lake Ontario shoreline in Clarington, seen across a bay under grey clouds
Darlington Nuclear Generating Station on Lake Ontario in Clarington, near the eastern end of the planned Toronto Third Line (file photo, November 2022). Photo: Robert T Bell / Wikimedia Commons, CC BY 2.0 (cropped and resized).

One of Ontario's biggest pension plans wants to help build the power line that would carry electricity under Lake Ontario into downtown Toronto. OMERS and Transmission Developers Infrastructure - Canada Co. (TDI), a company owned by Blackstone, announced Wednesday that they have formed a partnership to pursue the Independent Electricity System Operator's upcoming procurement for the Toronto Third Line.

The Globe and Mail reports that the bid also has backing from Kilmer Group, the investment firm owned by businessman Larry Tanenbaum. They will not be alone. According to the Globe, St. John's-based Fortis Inc. and British-based National Grid Ventures also plan to bid.

What the Third Line is

The province approved the project in January. Energy Minister Stephen Lecce approved the IESO's recommendation on Jan. 7, 2026 to build an underwater transmission line from near the Darlington Nuclear Generating Station to downtown Toronto and the eastern part of the city. The province says it would be the first line of its kind in Ontario and would deliver up to 900 megawatts of power.

According to IESO planning documents, the line would run about 65 kilometres from the Bowmanville Switching Station in Clarington to the Hearn Switching Station in Toronto's Port Lands. It would use high-voltage direct current (HVDC) technology and has a 2037-or-sooner in-service date. The company that wins will be responsible for route development, permits, regulatory approvals and Indigenous consultation.

The province says the need is growing. Toronto is now supplied by two transmission lines, from Manby Transmission Station in the west and Leaside in the east. Both are expected to begin reaching capacity in the 2030s, and the government expects Toronto's electricity demand to double by 2050. The IESO says the city faces "a period of unprecedented growth". It wants the new line to strengthen grid resilience and relieve emerging constraints on the existing system. Lecce said in January that the line would "enable 285,000 new homes, power new businesses, and create thousands of jobs".

Cost and timeline

When the project was announced, Lecce put the cost at an estimated $1.5 billion. The Globe reports that this figure comes from initial engineering estimates, with a possible range of $750 million to $3 billion. The project is expected to take seven to 10 years, and the IESO is expected to start collecting bids in mid-2027. The OMERS-TDI release also says the procurement is expected to launch in 2027. The IESO has already posted a draft request for proposals and opened a registry for transmitters who want to compete.

The pitch

TDI's main selling point is the Champlain Hudson Power Express. That roughly 545-kilometre underground and underwater HVDC line connects Quebec with New York City, and it entered commercial operation ahead of schedule in May 2026, according to the companies. They say the converter station built for it in Queens has many similarities to the work that will be required in Toronto's Port Lands. The Globe notes that although construction of the US$6-billion line took four years, it took 16 years from conception, partly because of permitting, consultation and regulatory issues.

"The Toronto Third Line represents an opportunity to invest in essential infrastructure designed to support Toronto's growing electricity demand and long-term system reliability," said Michael Hill, OMERS' global head of infrastructure and private equity. TDI chairman Brian Kubeck said that working with Indigenous communities, municipalities, regulators and suppliers would be central to the partners' approach.

For OMERS, the bid also fits a domestic investment push. The plan manages $152 billion for 665,000 members, according to the Globe. Its members include employees of municipalities, school boards, transit systems, electrical utilities and emergency services across Ontario. In April, chief executive Blake Hutcheson said OMERS would add at least $10 billion in new domestic investments over five years.

The line is also tied to Ontario's nuclear plans. Darlington is where the province is building the first small modular reactors in the G7. The Globe reported in January that the 900-megawatt line could carry all the power from three of the four 300-megawatt SMRs planned for the site.

Sources: Blackstone / OMERS / TDI (news release, Nov. 18) · The Globe and Mail (Nov. 18) · Ontario Newsroom (Jan. 7) · IESO: Toronto Third Line · IESO presentation (Oct. 1) · IESO presentation (Jan. 28) · IESO draft RFP · CBC News (Jan. 7) · Global News (Jan. 7) · The Globe and Mail (Jan. 7)